Barcelona Airport Runs On A Single Runway Until 26 November During Taxiway Works

Josep Tarradellas Barcelona-El Prat Airport has handled all flights on runway 06R/24L since 16 November, with runways 02/20 and 06L/24R closed until 26 November. Aena says the closure removes 1,441 slots, about 15% of capacity, while it builds a new rapid exit taxiway.
Every take-off and landing at Josep Tarradellas Barcelona-El Prat Airport is using the same strip of asphalt this week. Since Monday 16 November, all traffic has been concentrated on runway 06R/24L, the runway nearest the sea, while the crosswind runway 02/20 and the long inner runway 06L/24R stay closed. The arrangement lasts until Thursday 26 November, both days included.
Aena, which operates the airport, puts the cost at 1,441 fewer slots over the eleven days, roughly 15% of capacity. When it announced the works on 18 September, Aena said the cut had been coordinated in advance with airlines and with the bodies that allocate slots, so it was already built into flight schedules rather than imposed at short notice. According to La Vanguardia's report of 16 November, the work was planned more than a year ahead and placed in the winter season, when traffic at El Prat is lower.
What is being built
The closures make room for a new rapid exit taxiway that will link runway 02/20 with taxiway T4, letting landing aircraft leave the runway sooner. Aena values the project at €3.1 million. It covers new pavement, drainage, lighting and electrical supply, and has a construction period of twelve and a half months that began in September.
Aena does not claim the exit will add capacity. The declared capacity of the airport stays the same, the operator says, but the new link should reduce holding in the air and on the ground, manoeuvring and taxi times, with gains in punctuality, fuel burn, emissions and noise. Aena also expects it to make the preferred night-time runway configuration easier to use.
How the airport is operating
During the single-runway period the planned coordination allows about 22 arrivals and 22 departures an hour, the specialist site AeropuertosenRed reported on 17 November. It added that take-offs in non-preferred runway configurations are not authorised. Aena has said it will monitor the works and the operation throughout and may adapt the work to the weather.
One neighbour is spared. The town council of Castelldefels says on its airport information page that landings on 06L and departures from 24R are the operations that affect the town, so closing that runway adds no impact there.
After 26 November
Night work with occasional runway closures and taxiway restrictions continues until the first half of December, according to Aena, without disrupting normal operations. A longer restriction is planned later. Castelldefels lists a 52-day closure of runway 06R/24L within a works period running from January 2027 to June 2029, which would prevent parallel-runway operations and reduce capacity. The page does not give exact dates for that closure.